Our View: Is the Bay Bridge safe? We need to be convinced

06/29/2014 12:00 AM

06/29/2014 10:18 PM

From its outward appearances, the gleaming new San Francisco-Oakland Bay Bridge is an architectural marvel. But as we have learned since November 2011, its construction was troubled and the oversight process was deeply flawed.

For more than 21/2 years, Sacramento Bee reporter Charles Piller has been reporting on the construction of the $6.5 billion span, which replaced the double-deck eastern section that failed during the 1989 Loma Prieta earthquake. Piller’s first story in 2011 detailed how one bridge inspector had been disciplined repeatedly and falsified test results, and how his bosses papered it over. Appallingly, Caltrans allowed him to resign when he contested his firing.

Piller’s reporting has also disclosed how the company approved by Caltrans to provide critical welds was unqualified and did shoddy work. Rather than reject the cracked welds, Caltrans relaxed its standards. Almost beyond belief, the state turned to a company based in China for welds, rather than buying American steel and hiring U.S. steelworkers.

Caltrans tries to justify the decision by saying the Chinese company was brought on by the bridge’s main contractor.

But Caltrans awarded the contracts and ultimately is responsible, and it has become clear that, in its rush to just get the bridge done, the agency glossed over all sorts of considerations – from the subcontractor’s experience to outsourcing such a crucial piece of such an iconic project.

Between 2011 and last week, Piller reported many details, some of which would be funny, if public safety and $6.5 billion in public funds weren’t at stake. There was, for example, the inspector who used duct tape to keep water away from the rusting interior of the bridge.

In fact, some of the most basic flaws were written into laws by legislators who should have known better. A much-needed 2005 bill by then-Assemblywoman Loni Hancock, D-Berkeley, jump-started the long-delayed construction. But the bill exempted the Toll Bridge Program Oversight Committee from having to comply with California’s basic open-meetings laws. If the committee had met in the light of day, perhaps its members wouldn’t have made bad decisions, such as relaxing standards for welds, and doing business with a company halfway around the world that had never before built a bridge.

There are heroes in this story, including the bold experts who have risked the wrath of Caltrans by speaking out, and Piller himself who has been denounced by officials from Gov. Jerry Brown on down. Sen. Mark DeSaulnier, D-Concord, has conducted himself well. As chairman of the Senate Transportation Committee, he has confronted top Caltrans officials in ways that other legislators have not. He is headed to Congress, so there is room for a persistent legislator to step in.

We remain dumbfounded that federal transportation officials and Congress have been this stubbornly incurious about a bridge that is so important to interstate commerce. When he arrives on Capitol Hill, DeSaulnier ought to agitate for federal oversight.

Caltrans has tried to be more open lately, but it must come out of its defensive crouch, find world-class engineers and scientists who don’t have conflicts of interest, and pay them to review the work.

As we did in 2011, we urge Brown to insist there be a full and independent investigation to determine whether the bridge can withstand a massive earthquake, which was the point of spending $6.5 billion in the first place.

Editor's Choice Videos

Join the Discussion

The Modesto Bee is pleased to provide this opportunity to share information, experiences and observations about what's in the news. Some of the comments may be reprinted elsewhere on the site or in the newspaper. We encourage lively, open debate on the issues of the day, and ask that you refrain from profanity, hate speech, personal comments and remarks that are off point. Thank you for taking the time to offer your thoughts.

Terms of Service