Here is a tentative schedule of what sections of Interstate 5 in downtown Sacramento are closing when.
Friday, 8 p.m.
• All northbound lanes of I-5 closed from the Highway 50-Capital City Freeway interchange to L Street onramp.
• Two lanes of I-5 will be open from L Street to Richards Boulevard.
• Q Street offramp and I and L street onramps will remain open on northbound I-5.
Monday, June 9, 5 a.m.
• All lanes open for five days.
Friday, June 13, evening
• Southbound lanes of I-5 closed from Richards Boulevard to Highway 50.
• Two lanes will remain open for traffic exiting at J Street.
Monday, June 23, 5 a.m.
• All lanes open for four days.
Thursday, June 26, 8 p.m.
• Northbound lanes of I-5 closed from the Highway 50-Capital City Freeway interchange to the L Street onramp. Two lanes of I-5 will be open from L Street to Richards Boulevard.
• Q Street offramp and I and L street onramps will remain open from northbound I-5.
Thursday, July 3, 5 a.m.
• All lanes open for six days.
Tuesday, July 8, 8 p.m.
• All southbound lanes of I-5 closed from Richards Boulevard to Highway 50, except two lanes will remain open for traffic exiting at J Street.
Tuesday, July 15, 5 a.m.
• All highway-disrupting work complete.
For more information
• State Department of Transportation Web site for I-5 closure: www.fixi5.com.
Caltrans phone: (530) 741-4572.