Patterson growth effort hitting snags with Stanislaus County


gstapley@modbee.com
Bookmark and Share
email this story to a friend E-Mail print story Print reprintOrder reprints 0 comments
Text Size:

tool name

close
tool goes here

-- Patterson's bid to grow by nearly a third in one move — eventually making space for 10,000 badly needed new jobs — could hit a rough patch Wednesday.

Stanislaus County objects because developers would pay only a fraction of the cost to upgrade roads outside the proposed 1,119-acre West Patterson Business Park expansion.

Staff of a growth-guiding agency also frowns on the request because the city hasn't nailed down how it would come up with enough water and sewer capacity for the huge project, which could take 20 or 30 years to complete. Also, the city hasn't addressed loss of prime farmland or increases in air pollution and traffic noise.

  • ABOUT THE REPORTER

    alternate textGarth Stapley
    Title: Reporter
    Coverage areas: Regional water, growth, land-use and transportation; civil law, real estate fraud and special projects
    Bio: In his 19 years with The Bee, Garth Stapley has focused on city and county government
    Recent stories written by Garth
    E-mail: gstapley@modbee.com

City leaders say benefits from stores and other industry outweigh the downsides.

Local Agency Formation Commissioners will rule Wednesday night. Options include allowing the city to continue to try to work out kinks.

Patterson City Council members embraced the annexation idea in August, saying plans by Jeff Arambel and KDN Enterprises would "put Patterson on the map." They hope to capitalize on previous success that landed distribution centers for CVS pharmacy, Kohl's department store, Grainger, an office supplier and Internet giant Amazon.

The annexation would push the city's west edge up Interstate 5, from Sperry Avenue to Zacharias Road.

City and county negotiators could not strike a deal, mostly because the latter says county taxpayers could be left holding the bag on road improvements needed to handle the extra traffic created by the massive project.

For instance, the business park is expected to increase traffic 123 percent at Sperry's southbound interchange with Interstate 5, but the city plans to charge developers only 20 percent of the cost, county Public Works Director Matt Machado said in a letter.

A ramp heading north could see a 149 percent traffic increase, while developers are asked to pay 25 percent of improvement costs, Machado said. He listed 13 more road projects on Patterson's fringe, all with similar ratios.

First test of farmland policy

City-county agreements help proposals but aren't required for LAFCo approval. The panel is composed of two county supervisors, two representatives of cities and a member of the general public; any is replaced by an alternate if they can't attend. Neither of the city representatives comes from the county's West Side.

The annexation could present the first test of LAFCo's new farmland preservation policy, adopted in September despite protests from eight of the county's nine cities. It requires that cities come up with strategies that could require permanently preserving an acre of farmland elsewhere for every acre to be developed, or a voter-approved growth boundary.

Patterson leaders initially liked the idea of acre-per-acre mitigation but changed their minds to the dismay of farming advocates; doing so could cost developers more than $16 million, a report says. The city presented an agricultural preservation plan as required — with no strategy for lessening the blow to farmland, saying that would be too expensive.

City leaders say they'll require that development be about twice as compact as the adjacent business park. Also, it's not possible to guide growth toward poorer soil because the city essentially is surrounded by prime farmland, a report says.

Farm advocates sued LAFCo in the spring, after commissioners approved a 960-acre annexation to Ceres and before they adopted the new farmland policy. The panel should have required that Ceres do something to save dwindling agricultural land, the lawsuit says.

A Stanislaus County Superior Court judge ruled in LAFCo's favor in November, but farming advocates appealed and the case has yet to be resolved.

Patterson updating plans

LAFCo planners also take issue with the fact that Patterson has 1,220 vacant acres within the city limit. That's about 31 percent of the city and should be developed before Patterson adds more area, the theory goes, and annexing more "may actually discourage infill development in these areas," a report says.

Patterson is updating plans to show how future water and sewer needs will be met, and that shouldn't be held against the city, leaders say.

Fire protection, on the other hand, should pose no problem, because the city's fire department has reached a deal with the West Stanislaus Fire Protection District, which covers rural areas outside the city. In fact, the two agencies in coming years intend to form a joint powers authority, perhaps similar to the recent merger of Modesto and Salida fire stations and the county fire warden's office.

Developers would pay fees to build a new fire station and to cover costs of two more deputy sheriffs; the county Sheriff's Department already provides police services to Patterson under a contract.

The meeting will start at 6 p.m. Wednesday in the basement chamber at Tenth Street Place, 1010 10th St., Modesto.

On the Net: www.stanislauslafco.org/info/reports.htm.

Bee staff writer Garth Stapley can be reached at gstapley@modbee.com or (209) 578-2390.